Centrus President and CEO Daniel Poneman said on March 23 that the company has kept construction of a cascade of 16 AC100M centrifuges on track despite the pandemic. The facility is being built ...
The facility is under construction at Piketon, Ohio. The HALEU Demonstration Program (Image: Centrus) Centrus is licensing and constructing the cascade of 16 AC100M centrifuges to demonstrate ...
The American Centrifuge Plant at Piketon (Image: Centrus) The contract includes licensing, constructing, assembling and operating AC100M centrifuge machines and related infrastructure in a cascade ...
When Centrus’s cascade of 16 AC100M centrifuges is up and running as planned by Dec. 31, 2023, it will demonstrate the production of 20 kilograms (kg) of 19.75% enriched HALEU, as required by a ...
The scope of work under the contract includes licensing, constructing, assembling and operating the AC100M centrifuge machines and the related infrastructure at the plant located on Department of ...
Under a 2019 contract with the Energy Department, Centrus is constructing AC100M centrifuges to demonstrate HALEU production. The $115 million, cost-shared contract runs through mid-2022.